Progress in constructions (June 2018)

Classroom no. 8 is complete. Cupboards and shelves are in progress. Desks are also in the process of making. Timber has slowed the pace of furniture. Offices are complete. Courtyard will be done by the end of this week.
The cowshed is almost complete, wall is also progressing on well. The northern side is finished. By the end of this week, the eastern side will be complete. We will be remaining with two sides.
 